Five Vessels Under Concurrent Repair, Advancing Through Record Milestones | Huafeng Shipbuilding’s Path of Tackling Challenges in Parallel for LNG/LPG Ship Repair
Release time:2026-11-21 Click:1719
Gathering Momentum
Located in the core industrial belt of the international shipping center, Huafeng Shipbuilding has always pursued a path of differentiated competitive development leading the regional market with a stronger sense of mission. As early as the initial stage of business expansion, the company took fully refrigerated LPG carriers as the entry point and took its first step in liquefied gas carrier repair. In 2023, the fully refrigerated LPG carrier MV DOUBLE IN docked at the Baiquan Base for a comprehensive overhaul, covering renewal of cryogenic liquid-phase pipelines, replacement of FH36 cryogenic steel plates, overhaul of cargo valves and safety valves, new installation of the ballast system and the vessel’s special survey, with a construction period of only 15 days. During the repair, all welded joints of the vessel’s cryogenic pipelines passed non-destructive testing (NDT) in one go, and the commissioning of the cargo handling system passed class survey acceptance at the first attempt. The solid and profound technical expertise was highly recognized by the shipowner.
The success of this initial trial gave the exploratory team the confidence and courage to further delve into liquefied gas carrier repair. Taking this as a starting point, the company officially launched systematic capacity building: establishing exchange and cooperation mechanisms with industry professional technical institutions, and sending technical backbones for on-the-job advanced training in batches; upgrading and renovating specialized repair yards, and preparing for the construction of a special zone for cryogenic component repair; sorting out and compiling special safety specifications and process manuals for liquefied gas carrier repair, and building a full-process management framework. In-depth exchanges and cooperation with professional forces have enabled the company to form a comprehensive understanding of customer needs, technical standards, personnel teams, hardware and site facilities for LNG/LPG carrier repair. It has also embarked on research and reserves of process technologies and production management systems, staying fully prepared for new challenges that may arise at any time.

Forging Ahead
In 2024, Huafeng Shipbuilding, with its capacity building gradually improved, embarked on a new journey. The continuous consolidation of software and hardware resources also attracted more attention from customers in the market. In the same year, the LPG carrier MV SC Eternal, with a ship age of nearly 30 years, docked at the yard for its five-year special survey. With a long service life, complex system conditions and numerous hidden hazards, the vessel posed a severe test to inspection and assessment, risk identification and construction organization. Rising to the challenge, the project team sorted out system operating conditions item by item and steadily advanced the special survey project. All repair tasks were successfully completed within 15 days, which not only tempered the comprehensive disposal capacity for aging gas carriers, but also accumulated solid practical experience for undertaking higher-end LNG carrier repair in the future.
Fortune favors the prepared mind. In September of the same year, the 174,000 m³ ice-class electric propulsion LNG carrier MV Ma Ge Li slowly berthed at the wharf of Huafeng’s Baiquan Base. Measuring 299 meters in length and 50 meters in breadth, the vessel is equipped with 6 Wärtsilä tri-fuel generator sets and 4 GTT No. 96 membrane cargo tanks with Invar steel walls as thin as 0.7 mm, boasting a total cargo tank capacity of 174,000 m³. At that time, it was the largest and most technologically advanced ice-class electric propulsion LNG carrier ever docked for repair in the Zhoushan region. Although Huafeng had accumulated solid experience in fully refrigerated LPG carrier repair, it was the first time for the company to undertake an ice-class membrane LNG carrier of such scale. Multiple challenges lay ahead for the project team, including ice-class special coating, propulsion system overhaul, membrane tank protection, and disassembly & inspection of cryogenic valves — marking a truly full-scale large LNG carrier repair project. As the saying goes, fortune favors the bold in the face of challenges. Upholding the work style of tackling technical difficulties and pursuing excellence, the project team pooled efforts from production, technical, safety and quality departments, advancing all projects steadily, safely and in an orderly manner step by step. In the end, all repair tasks successfully passed the acceptance inspection by the shipowner and classification society, with a total construction period of 26 days. This not only set a new record for the largest dimension of ice-class electric propulsion LNG carrier repair in the Zhoushan region, but also accumulated crucial practical experience for the company to fully delve into the field of large membrane LNG carrier repair.

Breaking Through Core Challenges
"To make remarkable achievements in LNG/LPG carrier repair" is the development goal set by Huafeng Shipbuilding, and also an inevitable choice aligned with the company's philosophy of technology leadership and quality-based operation. Liquefied gas carriers are mainly categorized into fully refrigerated LPG carriers, MOSS-type LNG carriers and membrane-type LNG carriers. Among them, membrane-type LNG carriers have become the mainstream vessel type for clean energy transportation today due to their large cargo capacity and outstanding economic efficiency. Meanwhile, the special materials of the cargo containment system and the -163℃ cryogenic operating conditions of membrane-type LNG carriers impose higher repair requirements. To seize the initiative in the high-end gas carrier repair market, Huafeng Shipbuilding has been devoted to in-depth research and steadfast practice for many years.
In November 2024, the company's special cryogenic component repair zone with constant temperature and humidity was completed and put into operation. Featuring dust-free, constant-temperature and constant-humidity functions, the zone is equipped with dedicated testing equipment and customized tooling fixtures, meeting the environmental requirements for repairing core precision components such as Invar steel parts, cryogenic valves and cargo pumps. Both its software and hardware facilities are at the leading level in the regional industry. In the same year, Huafeng Shipbuilding reached in-depth cooperation with BW Group (Singapore) and became its certified shipyard in China. The two sides collaborate on technical exchange, standard co-development and project coordination for gas carrier repair. Leveraging BW Group’s global fleet resources and industry experience, the company further improves its process system and management standards for gas carrier repair. Meanwhile, the building of a full-chain repair capability covering construction management systems, tooling equipment, technical talents, and quality & safety control has been taking shape rapidly and orderly.
The accumulation of capabilities soon translated into a cluster of orders in the market. In 2025, the company completed repair projects for more than 10 LNG/LPG carriers in total, covering MOSS-type, membrane-type LNG carriers and fully refrigerated LPG carriers. Among them, the MOSS-type LNG carrier MV Dong Fang Neng Yuan docked in March and the No.96-type LNG carrier MV Si Pu Ni Ke docked in April, with ship ages of 23 and 20 years respectively. Both are aging vessels with complex conditions, and their repair cycles both reached 55 days. The capabilities of inspection and assessment, hidden defect disposal and system commissioning under complex conditions have been repeatedly tempered, and the company's comprehensive management and control capability for various vessel conditions continues to advance. In the same period, multiple LPG carriers including the MV Ai La, MV Da Mo and MV Hai Wei Tan Suo successively completed routine dry docking, special surveys and overhaul projects, with the shortest single-vessel construction period of only 16 days. The standardized repair process has become increasingly mature. By this time, everything was in place, awaiting only the right market opportunity.
Making Breakthroughs
The long-awaited market opportunity finally arrived. In 2026, the company’s gas carrier repair orders continued to grow steadily, with projects of various vessel types and conditions launched one after another. The standardized single-vessel repair procedures, schedule control and quality assurance capabilities have been continuously refined, laying a solid capability foundation for undertaking larger-scale cluster repair tasks.
More than a month before the official commencement, the company made overall planning and arrangements for the key and difficult projects of the five-vessel concurrent repair in advance. On the basis of existing technical and personnel reserves, it optimized dry dock allocation and manpower scheduling in combination with each vessel’s repair list and type characteristics, organized special technical re-training and re-assessment, deployed core technical personnel to each individual vessel project team, and made full preparations for protective support materials and tooling equipment. The team’s work style of scientific prudence and efficient execution kept the production rhythm of the five-vessel simultaneous repair stable and orderly. Key processes of each vessel progressed on schedule, and core inspections passed acceptance at the first attempt, winning high recognition from all shipowners. Meanwhile, it has successfully filled the historical gap in the cluster-based overhaul and modification of multiple LNG/LPG carriers in China. With this achievement, Huafeng Shipbuilding has completed a remarkable transformation from a "follower" to a "regional leader" in the field of LNG/LPG carrier repair.
Proactively adapting to the green transformation of the shipping market and striving to be a leader rather than a follower in clean energy vessel repair is the consistent development direction Huafeng Shipbuilding has always upheld. The market has every reason to believe that it will achieve more remarkable feats in the future.